NRW

River Wye: programme of alternative mitigation work

Note of field visit to upper Lugg and Arrow

 

Date:  15th April 2015

Venue: upper Lugg and Arrow catchments

 

Present:

Jason Jones                        NRW

Stephen Marsh-Smith          WUF

Tony Norman                    Upper Lugg & Arrow Fisheries Association

Stuart Smith                       WSA

Mike Timmis                      WSFOA

Peter Gough                      NRW

 

Apologies:

Rob Denny                          Monnow Rivers Association

Simon Evans                       WUF

Seth Johnson Marshall         WUF & WSFOA

David Revill                        Wye LFG

 

Introduction

PG introduced the purpose of this visit which was an inspection of weirs on the Welsh reaches of the Lugg and Arrow.  A shared view of priority of tackling these barriers compared to other mitigation activities would then be developed.

 

Barriers to migration

The following weirs were inspected:-

 

Lugg

Boultibrooke Weir (also known as Saw Mill).  Number 26 (Lugg) on NRW listing

Concrete baulk constructed by WUF in September 2011.

Agreed that his facilitated salmon passage (and probably also trout), and difficulty rating lowered.

Weir still prevents passage of minor species, and is therefore not WFD compliant.

CONCLUSION – NO ACTION REQUIRED UNDER AM

 

Boultibrooke Bridge Weir.  Number 27 (Lugg)

Weir much lower than previously assumed, at about 0.8m.

Low priority for salmon (and trout).

CONCLUSION – NO ACTION REQUIRED UNDER AM

 

Dolley Green Weir.  Number 28 (Lugg)

Relatively high and broad weir that will clearly obstruct salmon in range of flows.

Salmon know to have reached this point, but no further, in recent years.

Recent attempt by WUF to amend weir lead to structural problems and weir was stabilised with no benefit to migration achieved.

Option identified:            interim lowering of weir crest, to be followed by assessment of upstream bank stability and fish migration performance.

Subsequent weir removal may follow.

CONCLUSION – PRIORITY 1 FOR ACTION UNDER ALTERNATIVE MITIGATION PROGRAMME

Action:-                                Explore preferred option with landowner            ACTION: WUF

                                Confirm any heritage listing                                         ACTION: JJ

Confirm funding and partnership options             ACTION: PG

 

Arrow

Llanpica Weir.  Number 24 (Arrow)

Relatively low head, long diagonal stone-pitched weir.  Still supporting abstraction to old fish farm.

Salmon known to have reached this area in 2014, but failed to pass weir.

Weir is difficult for migration.

Options identified:          EITHER construction of half-width rock ramp, probably on LHS

OR lowering of half of weir, probably LHS

CONCLUSION – PRIORITY 1 FOR ACTION UNDER ALTERNATIVE MITIGATION PRIOGRAMME

Action:                                  Confirm whether there is extant abstraction licence        ACTION JJ note there is a confirmed extant abstraction licence here, but permitting only a 50% abstraction

                                                Confirm any heritage listing                                         ACTION: JJ

Open liaison with weir owner                                     ACTION: WUF

Confirm funding and partnership options             ACTION: PG

 

Conclusion

The group concluded that we have 2 high priority weirs for action ASA)P: Dolley Green and Llanpica.

 

Prioritising works

We previously agreed that we need to prioritise the top 3 in each of the main categories of work.

As a first stab:-

 

Work                                     Site                                                                        Approximate Cost

Barriers                                                Dolau Green – rock ramp                                             £30k

Llanpica – pre-barrage or removal                            £25k

Crucorney – rock ramp                                                  £40k

 

KRC                                        Upper Ithon (JJ paper)                         £90k (can be spread across several years)

Other KRC sites                                 £50k – £100k

 

Riparian management   sites tbc                                               £7 per metre

 

Instream habitat              Upper Irfon                                        £5k

Other sites tbc                                  £5k per site

 

 

The group now agrees to prioritise the barrier works at Dolley Green and Llanpica, but to have a set of KRC sites as reserve projects.                            

ACTION: ALL TO PROVIDE ANY FURTHER COMMENTS ASAP

 

Next meeting

TBC

 

 

 

End

©2021 wye salmon association

Facebook